CMA New Batches Starting from Upcoming Wednesday, Enroll Now                 Best & Oldest CMA Coaching Institute in North India                 Achieved an Impressive Total of 100 CMA All India Ranks Across The Last 15 Attempts                 CMA Offline / Live / Recorded Classes Available                 CMA New Batches Starting from Upcoming Wednesday, Enroll Now                 Best & Oldest CMA Coaching Institute in North India                 Achieved an Impressive Total of 100 CMA All India Ranks Across The Last 15 Attempts                 CMA Offline / Live / Recorded Classes Available                

Final PN-16 Strategic Cost Management Quiz 6

/25
0 votes, 0 avg
0
Created on By CA Sonal Saboo

CMA Final

Final Strategic Cost Management PN-16 Quiz 6

This quiz is based on the CMA Strategic Cost Management paper.
Each question is multiple-choice with 4 options, and only 1 option is correct.
Attempt the quiz to test your understanding of CMA SCM concepts.

1 / 25

Category: Strategic Cost Management PN-16

1. Which of the following statements about Learning Curve is incorrect?

2 / 25

Category: Strategic Cost Management PN-16

2. Limitations of the Learning Curve approach include –

3 / 25

Category: Strategic Cost Management PN-16

3. A Learning Curve describes:

4 / 25

Category: Strategic Cost Management PN-16

4. Activities A, D and F merges at the event 6. If the earliest finish times of A, D and F are respectively 13, 17 and 8 then the earliest time of Event 6 is –

5 / 25

Category: Strategic Cost Management PN-16

5. A critical path is –

6 / 25

Category: Strategic Cost Management PN-16

6. Which of the following is not a notable challenge while scheduling a project?

7 / 25

Category: Strategic Cost Management PN-16

7. The optimum duration is the –

8 / 25

Category: Strategic Cost Management PN-16

8. Critical Path Method is good for –

9 / 25

Category: Strategic Cost Management PN-16

9. Which of the following represents reduction in project duration?

10 / 25

Category: Strategic Cost Management PN-16

10. The slack times of Tail and Head events of Activity P are 10 days and 4 days respectively. If the Free float of the Activity P is 12 days then the Total float would be –

11 / 25

Category: Strategic Cost Management PN-16

11. The activity that must be completed prior to the start of an activity is called –

12 / 25

Category: Strategic Cost Management PN-16

12. Which of the following is incorrect?

13 / 25

Category: Strategic Cost Management PN-16

13. The Normal duration and Normal cost of an activity are 10 days and Rs. 350 respectively. The cost slope is Rs. 75 per day. If the Crash duration is 8 days then what is the Crash cost of the activity?

14 / 25

Category: Strategic Cost Management PN-16

14. The reduction in project time normally results in –

15 / 25

Category: Strategic Cost Management PN-16

15. A PERT activity has an optimistic time of 3 days, pessimistic time of 15 days and an expected time of 7 days. What is the most likely time of the activity?

16 / 25

Category: Strategic Cost Management PN-16

16. Solution of problems of Crashing has to be started by applying the technique on –

17 / 25

Category: Strategic Cost Management PN-16

17. In a project planning Free float can affect which of the following?

18 / 25

Category: Strategic Cost Management PN-16

18. Optimistic time and pessimistic time of an activity are respectively 4 days and 16 days. Variance of the duration of the activity will be –

19 / 25

Category: Strategic Cost Management PN-16

19. The amount of time by which an activity can be delayed without affecting the project completion is called –

20 / 25

Category: Strategic Cost Management PN-16

20. Following data refers to a project Network. What will be the Critical Path? Activity 1 – 2, 2 – 3 ,3 – 4, 1 – 4, 2 – 5, 3 – 5, 4 – 5 Duration 2 Days, 1 Day, 3 Days, 3 Days, 3 Days, 2 Days, 4 Days

21 / 25

Category: Strategic Cost Management PN-16

21. Which of the following statement is not true?

22 / 25

Category: Strategic Cost Management PN-16

22. The time by which the activity completion time can be delayed without affecting the start of the succeeding activities is known as –

23 / 25

Category: Strategic Cost Management PN-16

23. For an activity the pessimistic, most likely and optimistic times are respectively 10, 6 and 2 days. The expected duration of the activity is –

24 / 25

Category: Strategic Cost Management PN-16

24. A PERT Network has nine activities on its Critical Path. The Standard Deviation of each activity on the Critical Path is 3. The S. D of the Critical Path is –

25 / 25

Category: Strategic Cost Management PN-16

25. In PERT Chart, the Activity time distribution is -